Change orders: how to price, document and get paid for extra work

By cheapdocs Editorial Team · Updated · 8 min read · US, UK, AU, CA

Written from the official sources listed below. Not reviewed by a lawyer — see how we check our content.

Short answer: A change order is a signed agreement to change the scope, price or timing of work already under contract. The rule that protects you is simple: no extra work without a written change, priced and signed before you start — or, if work must start immediately, a written instruction followed by pricing within days. Watch for notice deadlines in your contract; missing them can forfeit a valid claim.

What counts as a change

Anything that alters the agreed scope, specification, quantities, sequence, access or timing can be a change — including a client's 'quick tweak', a design revision, unforeseen site conditions (if the contract allocates that risk to the client), or a delay caused by the client. Even outside construction, the same applies to freelance projects: a new page, an extra revision round or a different platform is a change to the statement of work.

Changes can also happen by conduct. If a client directs extra work without a formal change order and you do it, you may still have a 'constructive change' claim — but it's far harder to prove and price than a signed change order.

Notice and time bars

Many contracts say that if you don't notify a change or claim within a set period — often 7 to 28 days — you lose the right to extra time or money. Courts in the UK and Australia generally enforce clear time bars, and US courts often do too, especially in public contracts. Diarise every notice period in your contract and send a short written notice as soon as you think something might be a change, even before you know the cost.

Pricing a change

  • Lump sum: quote a fixed price for the change. Best when the work is clearly defined.
  • Time and materials, with a not-to-exceed cap: useful when the extent is uncertain; agree rates and markup in advance.
  • Contract rates: use the unit rates or schedule of rates in your original contract where they apply.
  • Include knock-on costs: extended site overheads, re-sequencing, extra supervision, re-testing and any effect on other trades.
  • Agree the markup for overhead and profit in the original contract, so you're not negotiating it under pressure on every change.

Time is money too

A change that adds work usually adds time. The change order should state the new completion date or the number of days' extension. If it doesn't, you may still be bound by the original date — and exposed to delay damages (liquidated damages) for work the client asked you to add. For freelancers, adjust delivery milestones and the payment schedule in the same document.

How standard contracts handle it

  • United States: the AIA family uses a Change Order (G701), signed by owner, contractor and architect, and a Construction Change Directive (G714) when the owner directs work before price and time are agreed.
  • United Kingdom: JCT contracts deal with 'Variations' instructed by the contract administrator; NEC contracts use 'compensation events', with strict notification periods — typically eight weeks — that can extinguish a claim if missed. The Construction Act gives a statutory right to adjudicate disputes over variations.
  • Australia: AS 4000 and AS 2124 deal with 'variations' directed by the superintendent; payment claims under state Security of Payment Acts can include variation amounts, giving you fast adjudication if they're disputed.
  • Canada: CCDC 2 distinguishes a Change Order (agreed scope, price and time) from a Change Directive (instructed before agreement, with valuation later). Ontario's prompt payment and adjudication rules apply to amounts properly invoiced, including changes.

A change order checklist

  • Reference the original contract and a change number.
  • Describe the change precisely, with drawings or a revised SOW attached.
  • State the price adjustment (or the pricing method and cap) and when it's payable.
  • State the time adjustment and any revised milestones.
  • Confirm everything else in the contract is unchanged.
  • Sign by people with authority on both sides, before the work starts.

When the client won't sign

Put your position in writing: what was asked, why it's outside the contract, and your price and time impact. If the contract lets you refuse unpriced extra work, say you'll start once the change is signed. If it obliges you to proceed on instruction, proceed and reserve your rights in writing. For disputes over payment, see what to do when a client won't pay, and for scope creep on creative work, our guide to kill fees, scope creep and change orders.

Frequently asked questions

Can I charge for a change after I've done the work?

Possibly, if the client asked for it and the contract doesn't bar the claim, but you'll be arguing about price after the fact. A signed change order before the work avoids that.

Do small changes need a change order?

Batch them. A weekly change log the client signs works well for small items; each one adds up.

Who can sign a change order?

Someone with authority under the contract — often named in it. A site manager's verbal OK may not bind the client.