Subcontract Agreement — Riverside Office Fit-Out
This Subcontract Agreement (the Subcontract) is made on December 1, 2026 between Northwind Creative LLC, a Texas limited liability company, of 400 Congress Ave, Suite 200, Austin, TX 78701 (the Contractor) and Precision Electric LLC of 88 Elm Street, Portland, OR 97205 (the Subcontractor) for work on the project described below.
1. Project and scope
| Project | Riverside Office Fit-Out |
|---|---|
| Location | 2100 Riverside Dr, Austin, TX 78741 |
| Owner | Riverside Holdings LP |
| Subcontractor licence | TECL 12345 |
The Subcontractor will furnish all labour, materials, equipment and supervision to perform the following work (the Work): Supply and install all electrical rough-in, panels, lighting and devices per drawings E-001 to E-210 (rev. C) and specification Division 26.
Flow-down. The Subcontractor is bound to the Contractor by the terms of the main contract between the Contractor and Riverside Holdings LP (the Prime Contract) as they apply to the Work, and assumes toward the Contractor the obligations the Contractor has toward the owner for the Work. The Contractor will provide relevant parts of the Prime Contract on request. If the Prime Contract conflicts with this Subcontract, the stricter requirement applies.
2. Schedule
The Subcontractor will start the Work on January 10, 2027, follow the Contractor's project schedule, and achieve substantial completion by April 30, 2027. The Subcontractor will promptly notify the Contractor in writing of any delay and its cause. Time extensions are granted only for delays outside the Subcontractor's control, and only to the extent the Contractor receives a matching extension under the Prime Contract where the delay originates there.
3. Contract sum and payment
The Contractor will pay the Subcontractor $184,500 for the Work, subject to approved change orders. The Subcontractor will submit progress claims by day 25 of each month for Work completed, in the form the Contractor reasonably requires.
The Contractor will pay approved claims within 30 days, less retainage of 5% (or any lower maximum allowed by Florida law). Retainage will be released on final completion and acceptance of the Work, delivery of closeout documents, and receipt of final lien waivers.
Lien waivers. With each progress claim, the Subcontractor will deliver a conditional waiver for the amount claimed and an unconditional waiver for the previous payment received, from itself and its lower-tier suppliers, using any statutory form required in Florida.
4. Changes
The Contractor may order changes to the Work. The Subcontractor must not perform extra work without a written change order signed by the Contractor stating the scope, price and time adjustment. Claims for additional cost or time must be submitted in writing within 7 days of the event giving rise to them.